Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Brookline Place Redevelopment Project

Look Ahead Schedule

30 de septiembre de 2019

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

Weekend Work: 9/28

1 BP: 

-Install of canopy BCH sign at North vestibule canopy.

2 BP: 

-Concrete sidewalk saw cutting.

Next Week:

Monday, 9/30 –Friday, 10/4:

Site Operations:

-Deliveries ongoing by all trades through Gates 1 and 3 – this will result in crane operations throughout the week

-Multiple excavators, loaders, bulldozers on site for site earthwork

Earthwork

2BP:

-Adjust catenary bases and install catenary light poles

-South fence along Washington to be disassembled and 1 BP entrance to be opened to the public (Friday, 10/4)

-Cast iron warning plates installation at NW radius

-Place sidewalk at NW corner, finish west bollard alignment and curbing

-Place site signage and lighting foundations

Façade/Roof:

1BP:

-Roof re-work to begin 10/3; crane on site off 1BP south into Washington Street

-Complete roof top unit wall and damper replacement

2BP:

-Exterior door hardware, caulking, soffits, pressure plates

-Exterior doors, loading dock framing and terracotta to be completed at West side

-North canopy framing and lighting installation

-Level 9 roof coping to be completed

Building Interior / Utilities:

2BP:

-Non-life safety mechanical/electrical/plumbing work

-Drywall install at IDF closets

-Sealed concrete flooring install

-Bike room graphics, paint, and millwork to be installed

-Loading dock overhead door start up and testing

-Paint touch ups

-Ceiling grid and tile install

Future:

Earthwork

2BP:

-Line striping at 1BP loading dock area

-Granite detectable warning pavers to be installed at BP West at drop off area

-Final soils, hardscaping, and sod placement

Façade/Roof:

2BP:

-Canopies completed

-Awnings install at South and Northeast elevations (week of 10/14)

Building Interior / Utilities:

2BP:

-Final Elevator inspections

-Miscellaneous accessories – bike racks, benches

More information about Boston Children’s at Brookline Place can be found at http://www.childrenshospital.org/about-us/expansion-and-renewal/brookline-place, and photos from the site can be found here.

The Brookline Place project team mailing address is: One Brookline Place, Suite 521, Brookline, MA 02445.